IF more than 20% of sessions fail at the turn budget, or observed usage sits far below a budget that was raised earlier → THEN raise the budget to the p90 of successful sessions, or decay it to the p95 → RESULT budget-limited failures stop wasting the work already done, or the excess-turn allowance stops being paid for.
The signal in the agentic log
- Raise signal: > 20% of sessions fail at the apparent turn budget.
- Decay signal: p95 usage is < 50% of the budget, or the workload shrank below 70% of its level at a prior raise.
- Field source:
TurnSeq,Outcome,SessionId,Cost.
The setup
- Accept the turn budget rightsizing recommendation.
- Raise → set the budget to roughly p90 of successful turns × 1.2.
- Decay → set it to p95 × 1.3.
The result
- Raising recovers the spend of sessions that were abandoned at the cap after doing most of the work.
- Decaying removes spend on turns the workload no longer uses.
- The recommendation remembers prior raises, so it will not flap back and forth.
Behind it
- Detector: turn budget rightsizing.
- Related: Stale scheduled automation.